We start with the basics

  • Re-zone the parcel of land if necessary.
  • Survey and soil test
  • Acquire permits to build
  • House plans
  • Prepare the site: tree removal and grading
  • Concrete footings
  • Underground plumbing
  • Foundation walls and pour slab
  • Build walls for floor joist and roof trusses
  • Set the trusses and frame the roof
  • Framers work on interior partitions

THEN

We get it moving Inside

  • Install subfloor and stairs
  • Heating and air contractors install A/C ducts
  • Plumbing rough-in and set the tubs
  • Set fireplace unit
  • Electrical rough-in
  • Exterior roofing complete
  • Soffits
  • Install windows
  • Exterior stone, brick, stucco and siding
  • Insulation
  • Dryall installation & Dryall finish

NEXT

Install the Necessity of living

  • Ceramic Tile
  • Interior trim and mantels
  • Exterior doors including garage doors
  • Exterior paint
  • Interior paint
  • Install cabinets, vanities and counter tops
  • HVAC
  • Plumbing finish …Fixtures, Septic or sewer hook-up
  • Electric complete
  • Appliances & A/C compressor installed

FINALLY

Put the finishing touches in place

  • Finish floors and install carpet
  • Pour concrete walks and driveway
  • Landscape and sod
  • Clean up the site and home
  • Move in and live happily ever after!